Earth Retention

Earth Retention systems are utilized to protect adjacent streets, buildings, utilities, etc. while an excavation takes place. Typically used methods are soldier pile and wood lagging, sheet piles, shotcrete & soil nails, tangent walls and secant walls. These systems can either be cantilevered, tied back or internally braced depending upon the wall height and soil conditions. They can also be structurally permanent or temporary, based upon the final construction requirements.

Soldier pile and wood lagging is a widely used and effective earth retention system. Soldier piles are drilled or driven at regular intervals along the perimeter of the excavation. Once the excavation starts, wood lagging is installed to maintain the excavated face. Soldier pile walls can cantilever or be laterally braced to suit the specific needs of the project.

Location

Memphis, TN

Project Facts

119 EA - 36-in dia. Soldier Piles ranging from 20ft-40ft long
16 EA - 48-in dia. Soldier Piles ranging from 38ft-44ft long
91 EA - 1180mm Tangent piles ranging from 45ft-60ft long

Scope

Installation of four (4) soldier pile walls with wood lagging and Value Engineer one (1) tangent wall to allow construction for widening interstate I-55 .

Location

Knoxville, TN

Project Facts

7,300 SF of design-build permanent earth retention
1,500 LFT of Soldier Piles installed
2,500 LFT of Tieback Anchors installed
3 EA - performance load tests
Proof tests performed on all tieback anchors

Scope

Designed and installed a permanent earth retention system with waterproofing and shotcrete facing to allow for the excavation and construction of a concourse addtition. Over 200 LFT of pinnacle Dolomite rock removed (12,000-45,000psi).

Location

Atlanta, GA

Project Facts

80 EA - drilled shafts ranging in diameter from 36" - 96" lengths varied (drilled to refusal)
20,000 SF - wood lagging shoring with drilled-in soldier piles

Scope

Design-Build temporary earth retention and drilled pier deep foundation for new parking deck.

Location

Cincinnati, OH

Project Facts

7,400 SF - Earth retention with untreated wood lagging
60 EA - HP12X53 at 35' in length
43 EA - Temporary Tieback Anchors

Scope

Design-Build temporary earth retention system for the construction of a new residential tower and parking garage.

Location

Toledo, OH

Project Facts

18,800 SF - Temporary earth retention with untreated wood lagging
83 EA - Drilled in soldier piles at 35'- 45' in length
98 EA - 14" diameter auger ties at 40' in length

Scope

Design-Build temporary earth retention system for the ozone treatment facilities to be installed at Collins Park Water Treatment Plant.

Location

Vincennes, IN

Project Facts

31 EA - drilled-in soldier piles 27ft in length
31 EA - rock tieback anchors 36ft in length
Exposed wall height: 21'

Scope

Furnish and install permanent earth retention system to stabilize tracks along riverside.

Location

Cincinnati, OH

Project Facts

5800 SF - Drilled in Soldier piles with permanent tieback anchors

Scope

Design-build permanent earth retention system and site wall for new building on church campus.

Location

Akron, OH

Project Facts

17,500 SF of temporary earth retention
110 EA - Driven Soldier Piles
110 EA - Tieback Anchors (Titan Bars)
275 EA - 16" diameter Tiedown Anchors at 45' in length

Scope

Designed, furnished and installed a temporary earth retention system to allow for the excavation of the proposed CSO Basin.
Also, Goettle designed, furnished, installed, and tested tiedown anchors using CFA methods.

Location

Swain County, NC

Project Facts

44 EA - HP 14x73 galvanized Soldier Piles at 40ft in length (avg.)
114 EA - DCP 4-strand Tieback Anchors at 50ft in length (avg.)
7,500 SF of untreated wood lagging
7,500 SF of precast lagging

Scope

Furnish and install design-build permanent earth retention system for slide remediation.

Location

West Union, WV

Project Facts

75 EA - Pre-drilled Soldier Piles
155 EA - DCP tieback anchors
25,000 SF of precast concrete lagging panels

Scope

Furnish and install design-build permanent rock and soil retention system
Value Engineered from original design of soil nail wall.

Location

New Albany, IN

Project Facts

74ea. - pre-drilled soldier piles
119ea. - permanent tie-back anchors
26,000 SF of earth retention
47' maximum wall height
70,000 CY of excavation

Scope

Installed 710 LF of permanent rock and soil retention system consisting of soldier piles, concrete facing and tie-back anchors
Soils consisted of 10' of overburden clay, with hard shale for the remainder of the height

Location

Cleveland, OH

Project Facts

16,000 SF of Anchored Soldier Pile with wood lagging wall
6,720 SF of Anchored Tangent Pile wall utilizing CFA method

Scope

Furnish and install temporary earth retention system with bracing and supports for four utilities while work was being completed across excavation.

Location

Lafayette, IN

Project Facts

96 Ea. 18-in dia. Low-Overhead (LOH) Tangent Piles 52' approx. length, total drilling - 4992 LF
800 SF of Soldier Pile & Wood Lagging system for first 10ft of excavation
4,576 SF of Tangent wall
42-in dia casing 60' in depth for drop shaft

Scope

Installation of a drop shaft 55' deep inside 22ft square excavation to create a casting pit for Nanshan America
Utilized temporary earth retention systems, permanent earth retention systems, struts & walers, water extraction systems and tangent piles in existing Nanshan America building under low-overhead restrictions.

Location

Dayton, OH

Project Facts

41 EA - soldier beams placed utilizing 24" diameter continuous flight auger
41 EA - 40' long 52/16 TEI Anchors
9,200 Sq. Ft. Wood Lagging
79 EA - 16-in dia. tangent piles
Bracing at the top of both walls

Scope

Installation of 9,200 Sq. Ft. of temporary earth retention with 41 tieback anchors, and 79 tangent piles @ 16" in diameter

Location

Dayton, OH

Project Facts

17,000 SF of soil nail / shotcrete underpinning
2900 SF soldier pile wood lagging

Scope

Installation of permanent soldier piles with wood lagging including tiebacks and 17,000 SF of soil nail and shotcrete underpinning

When the retained soil cannot be de-watered, a sheet pile earth retention system is an effective solution. Sheet piles are steel sections in a wide variety of cross-sectional shapes – all with the ability to interlock with one another forming a continuous, watertight wall. The sheets are driven or vibrated into the ground. Cantilever walls are typical, but the sheet piles can be laterally braced to suit the specific needs of the work site. Being manufactured from steel, they offer a high strength material with excellent quality control.

Location

Cleveland, OH

Project Facts

136,000 SF Anchored Combi-Wall Bulkhead
203 EA - Pipe Piles (PAZ-54 & PAZ-60) up to 69ft in length
202 EA - Sheet Piles (NZ-14)
203 EA - Tieback Anchors (12, 17 & 26-strand) up to 220ft in length
2,000 LFT of Walers
30,000 tons of stone backfill
107,000 CYDS of excavated material

Scope

Furnish and install combi-wall bulkhead for stabilization of a massive hillside slope failure to protect the shipping channel along the Cuyahoga River and create public space. Goettle acted as the Prime Contractor.

Location

Terre Haute, IN

Project Facts

30,000 SF of Sheet Piles
8ft to 30ft cut height
300 EA - Driven Piles ranging from 60ft-80ft in length
30 EA - Hollow Bar Anchors at 50ft in length

Scope

Designed and installed a temporary earth retention system and deep foundations for the construction of a new main lifting station.

Location

West Virginia

Project Facts

1,935 EA - Driven Piles (HP 18x157) at 110ft in length
1,100 EA - Hollow Bar Anchors
310,000 SF of Sheet Piles
195,000cyds of excavation

Scope

Furnish and drive sheets, h-pile and earth retention system for future melt shop, tunnel furnance and misc. structures.

Location

East Chicago, IN

Project Facts

352 EA - King Piles at 50ft in length
425 EA - Bulkhead pairs at 50ft in length
425 EA - Deadman pairs at 30ft in length
325 EA - Tierods at 90ft in length
173 EA - Walers

Scope

Installation of a 2,200 LFT king pile wall as a remedy for the South Tank Farm to act as an oil control barrier using a sealed barrier wall system (cut-off wall) to prevent any harmful contaminants from entering the canal. The barrier wall system was designed to provide structual support for futre canal dredging operations.

Location

Pittsburgh, PA

Project Facts

108 EA - 60-in, 66-in & 72-in dia. King Piles ranging from 40ft to 60ft in length
107 Pairs of NZ-38 Sheet Piles
40 EA - 7, 8 & 9 strand rock anchors
44 EA additional exploratory borings to determine soil and rock

Scope

Furnish and install design-build deep foundation system, rock anchors and temporary retention system including a king pile river wall to create more real estate required to enlarge the landlocked treatment plant expansion.

Location

Cincinnati, OH

Project Facts

Phase 1:
140 EA - sheet piles at 80' length with internal bracing
144 EA - tieback Anchors
Approx. 60' exposed cut height

Phase 2:
162 EA - sheet piles at 60'-70' with 2,800 LF of internal bracing
60 EA - tieback anchors
2 EA existing 10' diameter sewer piles
40'-50' exposed cut height

Scope

Design-build temporary sheet pile earth retention system for a new diversion concrete structure and interconnecting piping to support future work of a new pump station.

Location

Cincinnati, OH

Project Facts

230 LF of Driven sheet piles and soldier piles with tieback anchors

Scope

Furnish and install permanent earth retention system to protect existing utilities from soil erosion.

Location

Lake Charles, LA

Project Facts

Sheet piles at an average of 40'
Work started in October 2015
Projected completion: August 2016
Man hours to date: 20,654
Estimated man hours at completion:37,500

Scope

Installation and extraction of 40' sheet piles by three crews using Linkbelt 218 HSL's x 3 with 44-50 ICE vibratory hammers

Location

Panama City, Panama

Project Facts

17,000 tons PS-31 sheets
230,000 cubic meters of cell fill
1,400 tons PZC-26 sheets
221,000 cubic meters dredging

Scope

Design-Build project
Installed 24' - 72' dia. cells
Installed 34' - 58' dia. cells
Construct 1,500 LF of bulkhead retaining wall
Completed to project schedule of 38 weeks

Location

Augusta, KY

Project Facts

13,200 SF of PZC-14 driven sheet piles ranging from 25ft to 90ft in length
10,000 SF of temporary earth retention
4,800 SF of shotcrete
1,500 LFT of rock bolts
24 EA - HP 12x53 driven piles at 50ft in length

Scope

10,056 man hours
Installed temporary earth retention system for American Municipal Power, Inc.

Location

Columbus, OH

Project Facts

35 EA - 9-5/8-in dia. Micropiles 75ft in length
Over 1,500 LFT of pressure grouted columns through existing footing
Over 15,000 SF of sheeting installed

Scope

Installation of sheet piles, micropiles and pressure grouted columns all under low-overhead (LOH) conditions to stabilize bridge foundation and abutment for CSX.

When an excavation takes place next to an existing structure, a secant or tangent pile wall can be an excellent solution. Tangent & secant walls are a series of interlinking or adjacent concrete drilled piers or piles installed along the perimeter of the excavation. This method of earth retention not only allows for a high degree of alignment flexibility, it provides a structurally stiff wall, which minimizes settlement concerns of the adjacent structures.

Location

Akron, OH

Project Facts

50 EA - 1180mm Secant Piles at 50ft in length with 9ft rock sockets

Scope

Installation of secant piles for future tunnel diversion structure and deep baffle drop shaft to improve the city's sewer infrastructure and reduce sewer overflows.

Location

Memphis, TN

Project Facts

119 EA - 36-in dia. Soldier Piles ranging from 20ft-40ft long
16 EA - 48-in dia. Soldier Piles ranging from 38ft-44ft long
91 EA - 1180mm Tangent piles ranging from 45ft-60ft long

Scope

Installation of four (4) soldier pile walls with wood lagging and Value Engineer one (1) tangent wall to allow construction for widening interstate I-55 .

Location

Pittsburgh, PA

Project Facts

295 total Secant Piles installed
229 EA - 4ft dia. ranging from 70ft-90ft in length
66 EA - 3ft dia. Ranging from 70ft-90ft in length
70 EA - Soldier Piles
300 EA - Tieback Anchors
20,000 SF of lagging surface

Scope

Furnished and install design-build secant pile wall, soldier pile wall with wood lagging and tieback anchors for new bed tower addtion for UPMC.

Location

Columbus, OH

Project Facts

245 EA Secant Piles & 240 EA Pre-Excavation Grouting holes
50 EA - 1500mm Secant Piles at 107ft in length with 10ft rock sockets into 15,000psi Limestone
195 EA - 1180mm Secant Piles ranging from 31ft-100ft in length, 66 of which had 10ft rock sockets
Over 32,000 LFT of Pre-Excavation Grouting holes ranging from 131ft -182ft in length, drilling in-rock ranged from 7.5ft to 75ft.

Scope

Installation of secant piles and pre-excavation grouting for 5 drop shafts, 3 diversion structures and 4 relief structures for a 3.5 mile long tunnel designed to prevent sewage from overflowing into the Olentangy and Scioto Rivers during heavy rains.

Location

Rock Hill, SC

Project Facts

156 EA Secant Piles, 8 EA Drilled Shafts & Support of Excavation (SOE)
156 EA - 1080mm Secant Piles ranging from 35ft-62ft in length with 2ft-25ft rock sockets into Gabro rock formation
8 EA - 42-in dia. Drilled Shafts ranging from 20ft-40ft in length
Installed SOE with 2-4 levels of internal bracing

Scope

Installation of secant pile cutoff wall and drilled shafts for the Influent Pump Station (IPS).

Location

Racine, OH

Project Facts

121 EA 1080mm Secant Piles ranging from 80ft-110ft in length
Drilled through 3,200 LFT of concrete.

Scope

Furnish and install secant piles through existing concrete slab/bulkhead to replace a failure in one of the sheet pile cells.

Location

Columbus, OH

Project Facts

668 EA - 1180 mm and 1200 mm diameter secant piles at 70-90' length
Primary piles installed via CFA methods
Secondary piles installed with sectional casing
Total wall is 2,200 LF
Responsible for surveying and spoil removal

Scope

Design-assist partner for a partial cutoff wall and retaining/cutoff wall for a new stadium.

Location

Binghamton, NY

Project Facts

142 EA - 1500mm Secant Piles ranging from 36ft-45ft in length
17 EA - Caissons - 30-in dia. ranging from 35ft-40ft in length
Over 235 tons of reinforcing steel installed

Scope

Project was performed with two drill rigs drilling simultaneously on a 20,000 SF site.
Piles were drilled with segmental casing through 17,000psi Shale & Limestone.

Location

Miamisburg, OH

Project Facts

64 EA - 1500mm Secant Piles at 55ft in length
Drilled through sands, boulders/cobbles

Scope

Furnish and installed design-build permanent earth retention system for WWTF expansion utilizing BG-45 and oscillator.

Location

Cleveland, OH

Project Facts

16,000 SF of Anchored Soldier Pile with wood lagging wall
6,720 SF of Anchored Tangent Pile wall utilizing CFA method

Scope

Furnish and install temporary earth retention system with bracing and supports for four utilities while work was being completed across excavation.

Location

Lafayette, IN

Project Facts

96 Ea. 18-in dia. Low-Overhead (LOH) Tangent Piles 52' approx. length, total drilling - 4992 LF
800 SF of Soldier Pile & Wood Lagging system for first 10ft of excavation
4,576 SF of Tangent wall
42-in dia casing 60' in depth for drop shaft

Scope

Installation of a drop shaft 55' deep inside 22ft square excavation to create a casting pit for Nanshan America
Utilized temporary earth retention systems, permanent earth retention systems, struts & walers, water extraction systems and tangent piles in existing Nanshan America building under low-overhead restrictions.

Location

Dayton, OH

Project Facts

41 EA - soldier beams placed utilizing 24" diameter continuous flight auger
41 EA - 40' long 52/16 TEI Anchors
9,200 Sq. Ft. Wood Lagging
79 EA - 16-in dia. tangent piles
Bracing at the top of both walls

Scope

Installation of 9,200 Sq. Ft. of temporary earth retention with 41 tieback anchors, and 79 tangent piles @ 16" in diameter

A soil nail wall is constructed from the top – down, excavating in lifts of about five feet. At each lift, a soil reinforcement element – a soil nail – is installed and shotcrete is applied to the exposed earth face. This process continues to the required depth. Once completed, a reinforced soil mass is in place to resist the lateral earth forces. This type of earth retention can follow nearly any alignment and can be constructed in any type of soil that can stand vertically for five feet for a work shift. Soil nailing employs relatively small installation equipment and is well suited for close quarters.

Location

Knoxville, TN

Project Facts

7,300 SF of design-build permanent earth retention
1,500 LFT of Soldier Piles installed
2,500 LFT of Tieback Anchors installed
3 EA - performance load tests
Proof tests performed on all tieback anchors

Scope

Designed and installed a permanent earth retention system with waterproofing and shotcrete facing to allow for the excavation and construction of a concourse addtition. Over 200 LFT of pinnacle Dolomite rock removed (12,000-45,000psi).

Location

West Lafayette, IN

Project Facts

39 drilled soldier piles with tieback anchors
7300 sq. ft. of wood lagging
1925 sq. ft. of soil nails and shotcrete underpinning

Scope

Installation of permanent earth retention system and underpinning for existing railroad building for Purdue University.

Location

Pittsburgh, PA

Project Facts

5,200 SF of soil nail wall
220 ea. - epoxy coated soil nails
8" thick shotcrete facing

Scope

Installed an earth retention system consisting of 5,200 SF of shotcrete and soil nails for the Burchick Construction Company

Location

Dayton, OH

Project Facts

17,000 SF of soil nail / shotcrete underpinning
2900 SF soldier pile wood lagging

Scope

Installation of permanent soldier piles with wood lagging including tiebacks and 17,000 SF of soil nail and shotcrete underpinning

Integrated wall solutions combine that of permanent earth retention systems and in-situ concrete placement or the use of precast concrete panels. The first is to pour the liquid concrete material into forms against the existing PERS (Permanent Earth Retention System); this is so-called in-situ concrete. The other method used is called precase concrete, in which panels of specific size are manufactured in a central plant and later brought to the job site for fast, clean assembly.

Common applications of integrated wall solutions include; highway (DOT), railroad, retaining walls, bridge approaches and abutments.

Location

New Albany, IN

Project Facts

74ea. - pre-drilled soldier piles
119ea. - permanent tie-back anchors
26,000 SF of earth retention
47' maximum wall height
70,000 CY of excavation

Scope

Installed 710 LF of permanent rock and soil retention system consisting of soldier piles, concrete facing and tie-back anchors
Soils consisted of 10' of overburden clay, with hard shale for the remainder of the height

Slopes and embankments frequently experience settlement, stability and erosion problems. Richard Goettle, Inc. off­ers various solutions to these problems. From landslides to construction cuts into hillsides, remediation or an earth retaining structure is required to maintain the slopes’ stability.

Ground anchors, micro piles, anchored reaction blocks, and anchored retaining walls are all stability solutions that not only reinforce the soil but also control erosion. Anchored reaction blocks are ideal for newly failed slopes, applying loads to stabilize the soil. Ground anchors and micro piles create a stabilized ground reinforcement system which resists the driving forces of the slope. Anchored Retaining Walls are ground modification systems that include drilled or driven vertical elements that extend below potential failure planes. Drilled and grouted tieback anchors provide additional stabilization forces.

Location

New Albany, IN

Project Facts

74ea. - pre-drilled soldier piles
119ea. - permanent tie-back anchors
26,000 SF of earth retention
47' maximum wall height
70,000 CY of excavation

Scope

Installed 710 LF of permanent rock and soil retention system consisting of soldier piles, concrete facing and tie-back anchors
Soils consisted of 10' of overburden clay, with hard shale for the remainder of the height