Bluestone III Compressor Station

Location

Evans City, PA

Project Facts

Compressor - 172 micropiles (72 plumb and 100 battered)
Plant 3 Mat - 265 micropiles (all plumb)
2 tension/compression tests - one under each structure

Project Scope

Furnish and install 437 micropiles at two sites at the Compressor and Plant 3 Mat
Tension/compression tests

Completed For

MarkWest Energy Partners

Bluestone III Compressor Station

Location

Evans City, PA

Project Facts

Compressor - 172 micropiles (72 plumb and 100 battered)
Plant 3 Mat - 265 micropiles (all plumb)
2 tension/compression tests - one under each structure

Project Scope

Furnish and install 437 micropiles at two sites at the Compressor and Plant 3 Mat
Tension/compression tests