Manchester Creek WWTP
Location
Rock Hill, SC
Project Facts
156 EA Secant Piles, 8 EA Drilled Shafts & Support of Excavation (SOE)
156 EA - 1080mm Secant Piles ranging from 35ft-62ft in length with 2ft-25ft rock sockets into Gabro rock formation
8 EA - 42-in dia. Drilled Shafts ranging from 20ft-40ft in length
Installed SOE with 2-4 levels of internal bracing
Project Scope
Installation of secant pile cutoff wall and drilled shafts for the Influent Pump Station (IPS).
Completed For
The City of Rock Hill, SC
Manchester Creek WWTP
Location
Rock Hill, SC
Project Facts
156 EA Secant Piles, 8 EA Drilled Shafts & Support of Excavation (SOE)
156 EA - 1080mm Secant Piles ranging from 35ft-62ft in length with 2ft-25ft rock sockets into Gabro rock formation
8 EA - 42-in dia. Drilled Shafts ranging from 20ft-40ft in length
Installed SOE with 2-4 levels of internal bracing
Project Scope
Installation of secant pile cutoff wall and drilled shafts for the Influent Pump Station (IPS).