Project Facts

84 ea. 3 strand DCP 100 kip rock anchors +/- 65' for slide correction
20 ea. - 7" dia. micropiles at +/- 46' for site retaining wall
Including two performance tests and two inclinometers

Project Scope

Furnish and install 84 permanent rock anchors
Furnish and install 20 micropiles
For Burchick Construction Company
4 week time schedule
Equiptment: DK 725 and C7 drill rigs
2,108 man hours