Project Facts
Build 11' - 62' dia. cells
Build 3' - 38' dia. cells
Installation of 90,000 tons of cell fill
3,500 tons PS-31 sheets
Project Scope
Install North and South cofferdam for installation of new Seagate Complex
Complete to project schedule of 20 weeks
Completed For
USACE