Project Facts
Installed 200 x 24" augercast piles and 1,400 18" augercast piles x 40' in depth
Two compression load tests, six dynamic load tests and one lateral load test
58 ea. - 24" low overhead augercast piles x 40' in depth
3 ea. - 7' drilled shafts up to 35' long
Project Scope
Installed 64,000 LF of 24" and 18" low overhead augercast piles
Installed 7' drilled shafts x 35'
Three separate mobilizations
Completed For