Nippert Stadium Renovations
Location
Cincinnati, OH
Project Facts
Installed a temporary earth retention system
Installed caissons
12 week schedule - worked double shifts to meet schedule
Project Scope
48ea. - 30" to 78" dia. Caissons x 30'
10 of the caissons were hand dug
1,600 SF of temporary earth retention
33ea. - tieback anchors x 60' long with 20' rock sockets
Completed For
University of Cincinnati