LPV 148.02 Chalmette Loop Levee
Location
New Orleans, LA
Project Facts
Driven piles for the construction of 8 miles of T-wall for the New Orleans HDSRRS project
Project scheduled 26 weeks
Project Scope
Installed 5905 HP 14" x 117# x 152' long with up to a 2:1 batter
Total length of driven piles equal to 170 miles
Project involved a total of 9 crews and 16 cranes on project site
Completed For
USACE
LPV 148.02 Chalmette Loop Levee
Location
New Orleans, LA
Project Facts
Driven piles for the construction of 8 miles of T-wall for the New Orleans HDSRRS project
Project scheduled 26 weeks
Project Scope
Installed 5905 HP 14" x 117# x 152' long with up to a 2:1 batter
Total length of driven piles equal to 170 miles
Project involved a total of 9 crews and 16 cranes on project site