I-70 Mississippi River Bridge

Location

East St. Louis, IL

Project Facts

4 ea. - 10' dia. 120' long drilled shafts with 9.5' dia. rock sockets 14.5' long
Shafts drilled with temporary casing and slurry to rock
Rock socket diameter of 9'- 6" and 14' - 3" long

Project Scope

Installed 4 drilled shafts for Pier 13 on Illinois side of river
26 week schedule completed on time

Completed For

Missouri DOT

I-70 Mississippi River Bridge

Location

East St. Louis, IL

Project Facts

4 ea. - 10' dia. 120' long drilled shafts with 9.5' dia. rock sockets 14.5' long
Shafts drilled with temporary casing and slurry to rock
Rock socket diameter of 9'- 6" and 14' - 3" long

Project Scope

Installed 4 drilled shafts for Pier 13 on Illinois side of river
26 week schedule completed on time