Project Facts

74ea. - pre-drilled soldier piles
119ea. - permanent tie-back anchors
26,000 SF of earth retention
47' maximum wall height
70,000 CY of excavation

Project Scope

Installed 710 LF of permanent rock and soil retention system consisting of soldier piles, concrete facing and tie-back anchors
Soils consisted of 10' of overburden clay, with hard shale for the remainder of the height

Completed For